UPDATE: 12/01/22
- Utility contractor has submitted his construction schedule for the utilities. A complete schedule for construction was promised by Friday, December 2, 2022.
- Delivery is still scheduled for December 14, 2022 for the sheet pilings.
- City staff and Contractor met onsite concerning existing water system. A water system interruption is tentatively scheduled for December 8, 2022 for two valve installations. This will allow water system work in the future without further interruptions. Affected homeowners will be notified with a door hanger on Monday December 5, 2022. Should be less than 25 residences affected.
- Our next weekly meeting is scheduled to be part of the preconstruction meeting on December 6, 2022 at Heath City Hall.