- Sheet piling installation has been completed on the lake side of the causeway. The dewatering process is underway.
- A meeting has been set with AT&T onsite, Tuesday, January 17 to discuss conflicts of construction and the schedule.
- The contractor anticipates removing f collapsed culvert and concrete in that area next week.
- Trespassers continue to enter the work zone. Video was taken yesterday, January 12, of a bicycle rider attempting to go around the south gate. He spotted Mike Shook videoing him, and left back though the work zone.